The architect and I have made an inventory of all the preconditions required for obtaining the “omgevingsvergunning”. Some detail drawings are lacking and the architect will process these.
Last Thursday I’ve had a useful meeting with the fire department. The architect will process the required adjustments in the building plan as well as in the drawings.
The search for someone who is able to make static calculations rel. the building construction is now starting. Suggestions are welcome!